SMT process

Fast SMT changeover: take material search out of the changeover

Most changeover time is not machine setup but finding and checking material. The feeder placement table, kitting order and first-article pre-staging decide how short a changeover can get.

Read 4 min Author: Baichuan · Reviewed by: Technical Director

On a high-mix, low-volume line a dozen work orders a day is normal. Many people treat changeover time as machine setup time; stopwatch it and the picture changes: setup is about thirty percent, the other seventy is finding material, verifying it and waiting for the first-article result.

Where changeover time actually goes

Breaking one changeover down on a typical SMT line:

  1. Stop the line and remove the reels from the previous order
  2. Find material against the new order's BOM, from the rack or the warehouse
  3. Verify feeder and part number reel by reel
  4. Load material, fit the stencil, load the program
  5. Print, mount and reflow the first article, then judge it
  6. Pass the judgment and start volume production

Steps 2 and 3 are pure manual search and verification, and they grow linearly with the number of part numbers. Step 5 is waiting, which depends on how the first article is inspected.

What can actually be compressed is steps 2, 3 and 5. Setup itself (step 4) is quick when the program already exists, unless the model is new.

Three preparations

Generate the feeder table in advance

The feeder table is the drawing for a changeover. Manual layout is not just slow, it is error-prone: matching part numbers to feeders means reading the BOM by hand, one or two mistakes in dozens of feeders are common, and they only surface at the first article.

Generate the feeder table automatically per work order and model by aligning the feeder order in the machine program, the part numbers and quantities in the BOM, and the substitution rules. Issue it straight to kitting. With that done, no layout work is needed at changeover.

The second benefit is that kitting becomes an ordered action: which feeder first, which next, all from the table rather than judgement on the floor.

Issue kitting in feeder order

Lighting the rack in feeder order is the most direct approach. The person picking does not need to know the BOM, only to follow the lights: whichever bin lights is the reel to take, scan it, and the system verifies feeder and part number.

This merges "find" and "verify" into one action. Work that took two people half an hour is done by one person in a dozen minutes, and wrong material is stopped during kitting instead of reaching the machine.

For rack options see the smart rack; for retrofit scenarios see the retrofit rack.

Pre-set the first article and parameters

Waiting for the first article depends on two things: whether the program is in place and whether the judgment criteria are explicit.

The program version travels with the work order and is loaded at changeover, with no USB stick hunting. Criteria are configured in advance, covering which reference designators must be checked and what counts as a pass, so the result comes with a conclusion and no process engineer has to walk over.

Where the first article is checked by hand end to end, consider AOI or a first-article inspection station to bring the judgment down from tens of minutes to a few.

Two changeover flows compared

Step Manual feeder layout Auto-generated table with lit rack
Layout Filled in by hand from the BOM, 20–40 minutes Generated by the system, issued within minutes
Finding material Walking the rack against the BOM, by experience Bins light in feeder order, follow them
Verification Reel by reel by hand Verified at the scan, wrong material errors immediately
First article Waiting for a process judgment Criteria pre-set, result is the conclusion
Total changeover Grows linearly with part numbers Driven mainly by machine actions

Note the last row: changeover time never reaches zero. Dismantling, stencil changes and the first-article reflow all take physical time. What can be compressed is the manual search and verification.

Two things easily overlooked when changeovers are frequent

Leftover control. If the half reel left from the previous order has no recorded remaining quantity, the next use cannot tell whether it will last the order. Guiding by FIFO and leftovers first on the rack removes that judgement.

Changeover records. Start and end times, who took part, the orders before and after: this is the basis for improvement. Without records, all anyone can say is that a changeover felt fast or slow, with no way to find which step was slow.

Frequently asked questions

How far can changeover time be compressed

It depends on the equipment and product complexity. The compressible part is mainly material search and verification, which in manual mode usually take more than half of the changeover. Machine dismantling and the first-article reflow are physical time with limited room.

What data does automatic feeder table generation need

Three things: the feeder order in the machine program, part numbers and quantities from the BOM, and the substitution rules. Missing any one means the generated table needs manual patching and the benefit is discounted.

Is it worth it for small orders

The smaller the batch the more it is worth. With large batches there are few changeovers and the cost of manual layout is spread thin; with small batches and many models, changeovers are frequent and both the error rate and the time are multiplied.

Retrofit the existing rack or buy new

Look at the mechanical state of the rack. If the structure is sound and only the electronic indication is missing, adding light strips and a controller is enough; if the structure is worn or there are too few bins, a new rack pays off better. For the difference between the two forms see hardware products.

FAQ

Where does SMT changeover time actually go?
Breaking a typical line down, setup is about thirty percent; finding material, verifying reel by reel and waiting for the first article take the other seventy. The compressible part is concentrated in the manual search and verification.
What data is needed to generate a feeder table automatically?
The feeder order in the machine program, part numbers and quantities from the BOM, and engineering-approved substitution rules. All three are needed before the table can be issued directly.
How much search time does a lit rack save?
It depends on the number of bins and the variety. Once finding and verifying merge into a single scan, kitting that took two people half an hour is usually done by one person, and the exact figure has to be measured against the actual bin count.
What should a changeover record contain?
Start and end times, the orders before and after, who took part, and any exceptions with how they were handled. Without this the bottleneck step cannot be identified and speed is judged by feel.

Related reading

Next

Send us your line's problems

Describe your line's current state and the step that most needs fixing; we'll send a solution outline per process stage within 2 business days.

Address
Building 8, Room 303, Yilisheng Industrial Park, 602 Fengtang Avenue, Tangwei Community, Fuhai Street, Bao'an District, Shenzhen

Shenzhen Baichuan Zhike Technology Co., Ltd. · Since 2015 , serving electronics manufacturers across handsets, tablets, automotive electronics, FPC, WiFi modules, energy storage and more.

Used for this conversation only; never shared externally. By submitting you agree to be contacted about this request.

Questions?